Upgrade to Oracle ERP Cloud and Transition from CSV to CSA

Case study on Upgrade to Oracle ERP Cloud and Transition from CSV to CSA.

Client profile: Clinical-stage biopharmaceutical company developing immune, fibrotic, and immuno-oncology therapies, with operations across multiple U.S. sites.

Upgrade to Oracle ERP Cloud and Transition from CSV to CSA graphic

Executive takeaway

USDM upgraded a clinical-stage biopharma from Oracle E-Business Suite 11i to Oracle ERP Cloud and transitioned validation from CSV to a risk-based CSA approach, delivering on time in six months while saving the customer roughly 40% of the original validation estimate.

Delivery Timeline

6 months

to upgrade to Oracle ERP Cloud, migrate data, and validate the new system, completed during a pandemic and end-of-year holidays.

Cost Savings

~40%

saved against the customer's original validation estimate by moving from CSV to a risk-based CSA approach.

Validation Approach

CSV to CSA

leveraged new computer software assurance guidance to focus scripted, extensive testing on high-risk items only.

Before USDM

  • Running aging Oracle E-Business Suite (EBS) release 11i that needed to move to Oracle ERP Cloud.
  • A small project team and very limited budget that could not handle the entire validation alone.
  • A six-month window to implement, migrate data, and validate, with no plan to manage ongoing quarterly cloud releases.

After USDM

  • Live on Oracle ERP Cloud with the new system validated on time.
  • A risk-based CSA program that saved roughly 40% of the original validation estimate.
  • Reusable assets to keep the system validated through Oracle Cloud quarterly releases.

Challenge

A clinical-stage biopharmaceutical company that discovers, develops, and delivers transformative therapies for unmet medical needs needed to modernize its enterprise systems. Its clinical pipeline includes treatments for immune and fibrotic diseases as well as immuno-oncology therapies, supported by operations across multiple U.S. sites.

The company faced a tightly constrained modernization effort with several pressures converging at once:

  • It needed to upgrade its Oracle E-Business Suite (EBS) release 11i to Oracle Enterprise Resource Planning (ERP) Cloud.
  • The team had to implement the system, migrate data, and validate the new ERP system in six months — in the middle of a pandemic and during end-of-year holidays.
  • It needed a trusted partner to manage ongoing quarterly cloud releases without falling out of a validated state.
  • With a very limited budget and a small project team, the company could not handle the entire validation on its own.

Approach

USDM moved the customer from traditional computer system validation (CSV) to a risk-based computer software assurance (CSA) approach, concentrating effort where patient and product risk is highest. This kept the program aligned with 21 CFR Part 11 expectations while removing low-value scripted testing. CSA deliverables included:

  • Validation plan and high-level risk assessment (HLRA)
  • User requirement specification (URS), system requirement specification (SRS), and risk assessment
  • User acceptance testing (UAT) for low-risk items
  • Scripted and extensive testing for high-risk items
  • Installation qualification (IQ) and configuration verification
  • Immediate deviation handling

By tiering testing to risk and handling deviations immediately, USDM expedited the customer's validation efforts and protected data integrity throughout the data migration. The same risk-based discipline produced reusable assets so the customer could stay validated through each Oracle Cloud quarterly release rather than re-validating from scratch.

Results

USDM completed the customer's ERP validation on time, on a compressed timeline, and at a meaningfully lower cost than a traditional CSV effort would have required.

  • 6 months to upgrade, migrate data, and validate the new system.
  • The customer saved ~40% of the original validation estimate.
  • USDM leveraged new CSA guidance by moving the customer from CSV to a risk-based assurance model.
  • The customer gained assets to keep its system validated during Oracle Cloud quarterly releases.

“Thank you very much for your help, accommodating attitudes, and flexibility. This has not been an easy project for us, and you have been so flexible and willing to problem-solve with us to hit our timeline goals. Truly a great partner in this project!”

~ Senior VP & CIO

“The Validation team and QA went above and beyond to get this done. On behalf of the full implementation team, a big thank you! In my long career, the USDM validation effort is amongst the best I have ever seen!!”

~ Senior Director, Program Management

A risk-based CSA approach let this biopharma modernize to Oracle ERP Cloud in half a year and stay continuously validated through every quarterly release — faster, leaner, and audit-ready. Explore how USDM Continuous Compliance can do the same for your enterprise systems.

Validate faster with CSA

Modernize your ERP without slowing validation

See how a risk-based computer software assurance (CSA) approach can compress your Oracle ERP Cloud validation timeline and reduce cost while keeping you audit-ready through every quarterly release.

Explore CSA Services

Start here

Put AI to work in life sciences — with the right guardrails underneath.

Start with a structured AI Readiness Assessment: fixed-fee, executive-ready, and built to surface the highest-value workflows first.

Start here

Talk to USDM

Tell us what workflow or outcome you want to improve and we'll map the right AI, governance, and delivery path.

By submitting this form, you agree to USDM’s Privacy Policy and consent to receive communications from USDM. You can unsubscribe at any time using the link in our emails.